    Default seanmurphy265 Project 3 Almost Summer contest - Condenser Rack

    This for a chain dollar store. It's an elevator condenser rack 8'4" tall. The beam is a w6x9, the tube is 4x4x1/4", the angle iron is 3x3x1/4", and the gussets are 1/4" plate. This is made to their specs not mine. They gave me the drawing and I submitted a bid and won.

    This is actually the top.


    I used my Imig 200!


    The dimensions were from the center line of the beam.


    I really needed a third hand!


    I had to jack it up! I can't pick up the rack! I have it to where I can slide it on my trailer.
    Lincoln Eagle Engine Drive
    Everlast MTS 250
    Everlast Power Tig 225lx
    HTP Mig 2400
    Everlast Power Plasma 60C --> Just need to finish my CNC Plasma Table!
    Miller Spectrum 375 Extreme Plasma cutter
    Victor cutting torch
    HF 20 Ton Shop Press
    HF 4x6 Band Saw
    HF Air Compressor
    Northern Tool Drill Press


    www.murphywelding.com

  2. #2

    Default

    All for tubes squared and tacked!






    I have to turn the closest baseplate around... I had a brain fart, but it's only tacked! The beam is fully welded, but everything else is tacked. I will finish everything up tomorrow and spray with cold gal.
    Lincoln Eagle Engine Drive
    Everlast MTS 250
    Everlast Power Tig 225lx
    HTP Mig 2400
    Everlast Power Plasma 60C --> Just need to finish my CNC Plasma Table!
    Miller Spectrum 375 Extreme Plasma cutter
    Victor cutting torch
    HF 20 Ton Shop Press
    HF 4x6 Band Saw
    HF Air Compressor
    Northern Tool Drill Press


    www.murphywelding.com

  3. #3
    Join Date
    May 2012
    Location
    Disneyland
    Posts
    2,662

    Default

    Heavy Duty! Looks nice, congrats on winning the bid. How do you like the new Tweco gun? I bet the extra length comes in handy on a big/tall project like that.
    Long arc, short arc, heliarc and in-the-dark!

  4. #4

    Default

    Quote Originally Posted by Rambozo View Post
    Heavy Duty! Looks nice, congrats on winning the bid. How do you like the new Tweco gun? I bet the extra length comes in handy on a big/tall project like that.
    I like it and the extra length comes in handy, but you have to keep the cable from binding. It was worth the investment, because I was doing a lot of tacking, and moving the welder gets old. I'm anal retentive and refuse to pull a mig welder by the lead.
    Lincoln Eagle Engine Drive
    Everlast MTS 250
    Everlast Power Tig 225lx
    HTP Mig 2400
    Everlast Power Plasma 60C --> Just need to finish my CNC Plasma Table!
    Miller Spectrum 375 Extreme Plasma cutter
    Victor cutting torch
    HF 20 Ton Shop Press
    HF 4x6 Band Saw
    HF Air Compressor
    Northern Tool Drill Press


    www.murphywelding.com

  5. #5
    Join Date
    May 2012
    Location
    Disneyland
    Posts
    2,662

    Default

    Quote Originally Posted by SeanMurphy265 View Post
    I like it and the extra length comes in handy, but you have to keep the cable from binding. It was worth the investment, because I was doing a lot of tacking, and moving the welder gets old. I'm anal retentive and refuse to pull a mig welder by the lead.
    Yeah, I had a little MIG cart that I kept a dog leash on to pull it around without pulling on the cable.
    With as small as the inverters are getting I wonder when there will be a backpack MIG? There is a gas powered backpack stick welder for the truly mobile.

    Long arc, short arc, heliarc and in-the-dark!

  6. #6
    Join Date
    Apr 2012
    Location
    Washington State
    Posts
    723

    Default

    I was going to suggest putting a rope parallel to the welder lead to pull the welder around but you beat me to it Rambozo.

    I like the portable stick welder. The generator takes up more space than the welder. I bet it takes the lion's share of the weight on that backpack too.

    Nice project, Sean. I can't even imagine how you got it square and true all by yourself.
    Is it OK to want to break something just so that you can weld it back together?

    Everlast PowerTIG 185 Micro IGBT AC/DC Welder

  7. #7

    Default

    Looks like a decent job.

    did you use your little bandsaw to make the cuts?

    Any chance of future work at other stores?
    Everlast 200DX
    Everlast PT185
    Shoptask 3-in-1 (not currently in my garage, but I own it...)

    Any day on a motorcycle like this that ends just needing parts and labor is a good day.
    4.82, 158.67mph 1/8th mile 7.350, 200.35mph 1/4 mile

  8. #8

    Default

    I ordered everything pre-cut, but I ended up using a cutting torch because the beam was cut short.... The rack was no problem, I also made some parking lot bollards, indoor bollards, and two door frames. The door frames have been an absolute PTA.... I have built them before, but I have never installed them in an existing building. If I ever do them again, someone else will take the tin off the inside and outside of the building before I start. I have no intentions of ever working with this company again. I built the door frames like the job superintendant said, and had ordered the 8" channel pre cut to what he originally said. One of the doors is a 10' garage door and the tells me that he needs a 2' header after I have the frame laid out ready to weld. I had to add some of my 4x4 tubing drops to make the header. I also asked about the sheet metal work around the doors (I do not do this kind of work) and he tells me the door guy trims that out. He comes back later and asked me about the door trim, and says the welder always trims out the door. I never submitted any sheetmetal in my bid. Now I am going back and forth with the project manager and the superintendant, the project manager tells me to take care of it. I have no clue about triming out doors, and now I'm pissed! When we went over the 10' roll up door he said that he would take the double door out. Come time to install the frame I have to take the double door out, which added about 4 hours to my day because I do not have those type of tools. Everything has been vague and nothing is specific; now I kind of see why. Some of the other contractors have said that sometimes you do something one way, and then the next time you have to go back and redo what you have done. I have about $2,000.00 tied up in this job, and I do not have the money or the time to be jacked around. They get you by the balls and begin to squeeze them by subtily adding things that were not discussed in the begining. Then they say take care of it so the superintendant will OK your bill getting paid. I'd rather stick with small jobs!
    Lincoln Eagle Engine Drive
    Everlast MTS 250
    Everlast Power Tig 225lx
    HTP Mig 2400
    Everlast Power Plasma 60C --> Just need to finish my CNC Plasma Table!
    Miller Spectrum 375 Extreme Plasma cutter
    Victor cutting torch
    HF 20 Ton Shop Press
    HF 4x6 Band Saw
    HF Air Compressor
    Northern Tool Drill Press


    www.murphywelding.com

  9. #9
    Join Date
    Oct 2010
    Location
    Northern Virginia
    Posts
    1,323

    Default

    Quote Originally Posted by SeanMurphy265 View Post
    One of the doors is a 10' garage door and the tells me that he needs a 2' header after I have the frame laid out ready to weld. I had to add some of my 4x4 tubing drops to make the header. ... I also asked about the sheet metal work around the doors (I do not do this kind of work) and he tells me the door guy trims that out. He comes back later and asked me about the door trim, and says the welder always trims out the door. I never submitted any sheetmetal in my bid. ... Now I am going back and forth with the project manager and the superintendant, the project manager tells me to take care of it. ... he said that he would take the double door out. Come time to install the frame I have to take the double door out, which added about 4 hours to my day because I do not have those type of tools. Everything has been vague and nothing is specific; now I kind of see why. ... Some of the other contractors have said that sometimes you do something one way, and then the next time you have to go back and redo what you have done.
    Classic scope creep, unfortunately. Are they doing it on purpose, or are they just disorganized? When the project manager tells you to "take care of it", can you bill him by the hour for work that you didn't bid on, like removing the double door that someone else was supposed to remove?

    BTW Welcome back, FDCMiami, haven't heard from you in a while.
    DaveO
    Oxweld oxy acet gear
    IMIG 200
    PowerTIG 210 EXT... Amazing!

  10. #10
    Join Date
    Apr 2012
    Location
    Washington State
    Posts
    723

    Default

    Yeah, that sucks. Might be worth your while to do some studying on project management techniques if you plan on bidding in the future on large'ish projects with many moving parts. It's a hassle but sometimes you need to do the project management in order to protect yourself. I'd much rather just do my own job but on the bigger bids, if no one does the proper scoping and management of the deliverables, its the little guys who get the shaft.
    Is it OK to want to break something just so that you can weld it back together?

    Everlast PowerTIG 185 Micro IGBT AC/DC Welder

  11. Default

    Quote Originally Posted by undercut View Post
    Yeah, that sucks. Might be worth your while to do some studying on project management techniques if you plan on bidding in the future on large'ish projects with many moving parts. It's a hassle but sometimes you need to do the project management in order to protect yourself. I'd much rather just do my own job but on the bigger bids, if no one does the proper scoping and management of the deliverables, its the little guys who get the shaft.
    that's a pretty interesting philosophy you have there UC; hope it works out for you.

    at the risk of getting flamed i would like to suggest something, too late for this matter but maybe someone else will benefit from it. if i were building this in my driveway (or anywhere else for that matter) i would have built it one of two ways. 1. i would have built the framework for the legs, first one end, and then built the other end on top of that. trying to true up 4 by 4's that reach eight feet into the air is way to hard. one inch; one degree; .017. if you simply framed them by tacking a temporary piece of angle to the top and bottom, then built the rest and then stood them up it would have gone much better for you.

    2. second way, and this is what i would have done; i would have built the I beam frame first (coping the I's) then i would have built the two ends off of the top of the frame. it is so much easier to work when the components are laying flat.

    you made a number of serious errors on this job, just accept the fact that you were a little unprepared , learn from it and move on.
    '
    Last edited by fdcmiami; 10-10-2012 at 12:05 AM.

  12. #12

    Default

    Sounds like the kind of job you take a torch with you when you go back to after not getting paid...
    Everlast 200DX
    Everlast PT185
    Shoptask 3-in-1 (not currently in my garage, but I own it...)

    Any day on a motorcycle like this that ends just needing parts and labor is a good day.
    4.82, 158.67mph 1/8th mile 7.350, 200.35mph 1/4 mile

  13. #13
    Join Date
    May 2012
    Location
    Disneyland
    Posts
    2,662

    Default

    I've learned that with most jobs you need to get everything in writing and have the drawings approved before any work begins. Verbal agreements are never good with new customers. Specifying what you will not do is almost as important as what you will do.
    Last edited by Rambozo; 10-08-2012 at 11:19 PM.
    Long arc, short arc, heliarc and in-the-dark!

  14. Default

    too bad it had to go that way but they're not all like that; you might try assembling the involved parties in one place at one time and see what you can work out. wait until you get on a job that runs a year and they're taking 10% retention out of every draw, then they really got you. there's good money in miscellaneous metals but you need to know what your scope of work is ahead of time, in addition there are things that are expected to be done by the sub by default. guess you were lucky no one asked you about pumping concrete in around the frame. next time figure more money; by the way, why throw your money away by having your material precut. get, or use if you already have one, a good oxy/acet kit. i cut that light stuff with a #3 tip. very small kerf then a light grind. when all's said and done no one will know the difference.


    just noticed the condenser frame; did you cope the i's?

    i started reading the post about the issues with super and p/m. i should have started from the beginning.
    Last edited by fdcmiami; 10-08-2012 at 11:43 PM.

Similar Threads

  1. Project 4 SeanMurphy265 Almost Summer, Parking lot bollards
    By SeanMurphy265 in forum Heavy Equipment and Commercial Projects
    Replies: 14
    Last Post: 08-13-2013, 09:26 PM
  2. SeanMurphy265 Project 2 Almost Summer Contest - Tube Bender
    By SeanMurphy265 in forum Other Custom Fabrications
    Replies: 5
    Last Post: 08-24-2012, 05:05 PM
  3. SeanMuprhy265 Project 1 Handrails Almost Summer Contest
    By SeanMurphy265 in forum Heavy Equipment and Commercial Projects
    Replies: 18
    Last Post: 07-20-2012, 02:27 AM
  4. Project 6 Welding Table, Mean Green Contest, SeanMurphy265
    By SeanMurphy265 in forum Other Custom Fabrications
    Replies: 8
    Last Post: 06-09-2012, 02:41 AM
  5. Project 4 Mean Green Contest, SeanMurphy265, Stage Backdrop.
    By SeanMurphy265 in forum Other Custom Fabrications
    Replies: 3
    Last Post: 05-11-2012, 05:51 PM

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •